What are the timescales?
 

 

Join the EMQN at any time, gaining access to our network resources and meetings. However, make sure that you join in time to register for your selected schemes. The closing date for scheme registration is towards the end of July every year, with a discount for members registering before 30th June. Schemes typically run from October to January, with final reporting in April.


The timetable for the 2010 scheme is as follows:

ActivityStartFinish
EQA scheme registration 01.05.10

26.07.10

 

Sample distributionOctober 10October 10
Reporting period01.10.1016.01.11
Genotyping results published Reporting date + 7 days
Scheme assessments05.03.1106.03.11
Lab results published01.04.1101.04.11
Appeals process01.04.1114.04.11
Final scheme report published30.04.1130.04.11

 

 
 
 
 
 